1 |
MINISTRY OF ROYAL AIR DEFENSE |
12/32 |
CONSTRUCTION OF HOUSING APARTMENTS 80 Housing Facilities for Airbase |
Dhahran |
February 2011 |
18 Months |
Construction of Housing Complex comprise Apartments - 08 Buildings - 10 Complete civil, mechanical, electrical HVAC work, Fire Alarm System, Gas System TV/Antenna System and communication System, parking lot with the required access roads |
2 |
MADI M AL-HAJRI & PARTNERS CO |
|
CONSTRUCTION OF MODERN CRESCENT PLASTIC FACTORY |
2nd Industrial Dammam |
February 2012 |
18 Months |
Construction of Factory Plant area, Warehouse area, Factory offices & Security office. Complete civil, mechanical, electrical, HVAC work, and Fire Alarm System and Factory boundary wall. |
3 |
SAUDI ARAMCO OIL COMPANY |
6600027434 |
COMMUNITY CENTER AT AL-HASA |
Al-Hasa |
July 2011 |
18 Months |
Contractor shall provide all supervision, labor, equipment, tools and materials to Complete the following: One 7,300SM adult soccer field with running tracks; One 1,400SM children's soccer field; Two 900SM swimming pools for female & male users; One |
4 |
SAUDI ARAMCO OIL COMPANY |
6600019269 |
(RELEASE PURCHASE ORDER) UNDER BUILDING TRADES |
Dhahran |
December 2008 |
48 Months |
Contractor shall provide all supervision, labor, equipment, tools and materials to complete the following: Excavation, backfilling and grading, construction, design, pre-cast concrete works, interior & exterior finishing. |
5 |
MINISTRY OF DEFENSE AND AVIATION |
2/6 /124A |
CONSTRUCTION OF FACILITIES, BRIGADE 17TH IN EASTERN REGION – PHASE 1 |
Dhahran |
July 2009 |
18 Months |
Construction of Facilities for Military Equipment Parking Shed and Wheeled Vehicle Parking Shed Site clearing, asphalt, backfilling and grading, construction, design, street lighting, with all related architectural, mechanical, and electrical works |
6 |
SAUDI ARAMCO OIL COMPANY |
6600022060 |
CONSTRUCTION NEW MUSSALLA FOR TE & SD AT DHAHRAN |
Dhahran |
April 2009 |
10 Months |
Contractor shall provide all supervision, labor, equipment, tools and materials to complete the following: Excavation, backfilling and grading, construction, design, pre-cast concrete works, interior & exterior finishing, with all related mechanical |
7 |
SAUDI ARAMCO OIL COMPANY |
6600020573 |
CONSTRUCTION OF NEW TD ADMIN BUILDING |
Dhahran |
June 2008 |
14 Months |
Contractor shall provide all supervision, labor, equipment, tools and materials to complete the following: Excavation, backfilling and grading, construction, design, interior and exterior finishing, communication works, fire alarm, HVAC works, pre- |
8 |
MINISTRY OF DEFENSE & AVIATION |
2-6-127/A |
CONSTRUCTION OF BATTALION COMMAND BUILDINGS IN EASTERN PROVINCE |
Dhahran |
August 2006 |
18 Months |
Construction of Battalion Site Work and Complete Finishing Works (Civil/Electrical/Mechanical) & Sewer Treatment Plant |
9 |
SAUDI ARAMCO |
6600012796 |
TANAJIB CHEMICAL STORE & PERMANENT POWER SUPPLY |
Tanajib |
April 2005 |
May 2006 |
Construction of Steel Building for open Chemical Storage, closed Hazardous Material Storage building, Two Floor Office Building, HVAC system, Switch Board, Panels, Transformers, Holding Tank, Chemical Storage Underground Tank – 20000 USG Capacity, Pa |
10 |
SAUDI ARAMCO |
6600005522 |
CONSTRUCTION OF MAINTENANCE GARAGE |
Abqaiq |
January 2003 |
August 2004 |
Demolition/Removal of existing heavy maintenance building no. 1040, Construction of new Maintenance Garage pre-engineered steel building, HVAC, Fire Protection, New Electrical/Distribution Equipment & New Communication Facilities, Installation of Ove |
11 |
SAUDI ARAMCO |
6600053190 |
FIRE TOWER TRAINING BUILDING & FIRE WATER SYSTEM |
Dhahran |
May 2002 |
April 2003 |
Fire Water Supply System • Fire Water Tank Installation • Fire Tower Training Center Building Construction |
12 |
SAUDI ARAMCO |
44610/00 |
COMMUNICATION BUILDING - HARADH - GOSP II |
Haradh |
September 10, 2001 |
December 25, 2002 |
Contractor shall provide all supervision, labor, equipment, tools and materials to complete the following: Site clearing and demolition, excavation, backfilling and grading, construction, design & installation of communicating tower, DC system, inst |
13 |
SAUDI ARAMCO |
44628/00 |
DESALINATED WATER SUPPLY |
Ad-Danah |
September 05, 2001 |
November 15, 2002 |
Contractor shall provide all supervision, labor, equipment, tools and materials to complete the following: Site preparation, design, construct & installation of water tanks (18M & 11M diameter), construction of pump station, complete mechanical work |
14 |
SAUDI ARAMCO |
44378/00 |
COMPLETION OF HOME OWNERSHIP LOTS INCIII, PH1B1, AL-HASA |
Al-Hasa |
September 05, 2001 |
November 15, 2002 |
Contractor shall provide all supervision, labor, equipment, tools and materials to complete the following: Site clearing & demolition, excavation, backfilling & grading, water system, street grading & paving, street walkway & lighting, utility adju |
15 |
SAUDI ARAMCO |
44408/00 |
NEW JUAYMAH MAIN GATE |
Juaymah |
March 05, 2000 |
August 2001 |
Contractor shall provide all supervision, labor, equipment, tools and materials to complete the following: Site preparation, detour construction & removal, trench excavation, backfill & surface reinstatement, performance of all required demolition o |
16 |
ROYAL COMMISSION FOR JUBAIL & YANBU |
570-C31 |
REMOVAL OF INTERIM B1 PUMP STATION AT JUBAIL INDUSTRIAL CITY |
Jubail |
November 2003 |
February 2004 |
Contractor shall provide all supervision, labor, equipment, tools and materials to complete the following: Removal of civil & structural items, removal of electrical items, removal of mechanical items including tanks, pump station, HVAC system etc. |
17 |
MADI M. ALHAJRI & PARTNER CO. |
|
CONSTRUCTION OF MOSQUE |
|
05/1999 |
02/2000 |
Construction of mosque, site grading, excavation, backfilling, foundation, columns, construction of mosque bldg w/ utilities, complete civil, electrical, & mechanical works including HVAC, telephone, public sound system |
18 |
AL-HAJRI INDUSTRIAL WORKSHOP COMPLEX |
|
CONSTRUCTION OF WORKSHOP COMPLEX IN JUBAIL INDUSTRIAL CITY |
|
01/1997 |
01/1999 |
331-D52 Site preparation & development, construction of roads, walk ways, parking areas, erection of street lighting, sign & signals & sign boards, constructing the utilities (such as electrical pipes, cables, sewage & water pipes, communication cabl |
19 |
SILVER CRESCENT DISPENSARY |
|
CONSTRUCTION OF POLYCLINIC IN THOQBAH |
|
08/1996 |
05/1998 |
Site preparation & development, excavation, leveling & filling, foundations, installation of electrical & HVAC, telephone, CATC, computer network system, fire alarm, fire fighting system, complete furniture & equipments, clinic & apartment accessorie |
20 |
MADI M. ALHAJRI |
|
CONSTRUCTION OF MULTI STOREY VILLA IN ALKHOBAR |
|
01/1994 |
11/1996 |
Site preparation & development, design & engineering work, excavation for foundations, columns, beams, walls, complete concrete structure & masonry works, total plumbing, electrical works, HVAC, telephone & CATV works, interior & exterior finishing, |
21 |
SALINE WATER CONVERSION CORP. (S.W.C.C.) |
|
CONSTRUCTION & REPAIR OF CULVERTS IN JUBAIL-RIYADH HIGHWAY |
|
05/1994 |
02/1995 |
Construction of culverts, repair of culverts, thrust boring works & provide to tunnel 30" steel sleeve pipes beneath the existing SWCC lines A & B, provide drainage culverts beneath construction of roads & walkways |
22 |
MINISTRY OF DEFENCE & AVIATION (DIRECTORATE GENERAL OF MILITARY WORKS) |
|
MISSILE PROTECTION FACILITIES PROJECT (ALONG M&M CO. AS JOINT VENTURE) – PROJECT 13/12/1- D |
|
02/1416 |
02/1418 |
Site preparation, soil improvement, patrol road, road construction & pavement including traffic signs, walkways, construction of public yards, retaining walls, storm water system for entire site, water supply, irrigation system, sewer system, electri |
23 |
MINISTRY OF DEFENCE & AVIATION (DIRECTORATE GENERAL OF MILITARY WORKS) |
|
CONSTRUCTION OF MEDICAL WAREHOUSE COLD STORAGE IN DHAHRAN AIRBASE |
|
01/1993 |
01/1994 |
Construction of medical warehouse, construction & installation of cold storage for medical items, safety equipment installation, complete mechanical/HVAC/electrica l works |
24 |
MINISTRY OF RURAL AFFAIRS WATER & SEWAGE AUTORITY OF EASTERN PROVINCE |
|
CONSTRUCTION OF COMPUTER & EXHIBITION CENTER |
|
11/1993 |
06/1997 |
Site preparation & development, grading, leveling & excavation for foundation, construction of RCC footings, grade beams, column, floor & total interior finishing, installation of mechanical, electrical, sewage, HVAC, telephone system, roadway & park |
25 |
KING FAHD UNIVERSITY FOR PETROLEUM & MINERALS (KFUPM) DHAHRAN |
|
BUILDING ANNEXES PROJECT (DHAHRAN) |
|
11/1993 |
10/1996 |
Site preparation, grading, leveling, excavation & backfilling for drainage, raw & clean water system electrical telephone, CATV system & construction of roads, walkways, retaining walls, supply & fix transformers, irrigation & landscaping works |
26 |
ARABIAN PETROLCHEMICAL CO. |
|
PETROKEMYA OLEFINS PROJ. PROECT OFGO/A2-PO01358 |
|
05/1993 |
06/1993 |
Repair & maintenance program, removal of steel in area for repair, process system installation, cutting/ welding/fitting support structure & foundation |
27 |
ARABIAN PETROLCHEMICAL CO |
|
INSTALLATION OF MISCELLANOUS FOUNDATION PROJECT OFGO/A2/PO00918 |
|
12/1992 |
02/1994 |
Construction of pipe supports & pipe foundations, miscellaneous steel structure & foundations-foundation for electrical & process instrumentation, installation of hose box, extinguisher & cabinet foundations |
28 |
NATIONAL COMPANY FOR GLASS INDUSTRIAL ZOUJAJ |
|
CONSTRUCTION OF LABOR QUARTERS IN DAMMAM |
|
12/1992 |
03/1993 |
Site preparation, construction of complete labor quarters, painting sanitary works, electrical works, roads & pavement, fencing & gates |
29 |
ARABIAN PETROLCHEMICAL CO. |
|
PETROKEMYA OLEFINS PROJ. PROECT OFGO/VO-PO00913 |
|
08/1992 |
12/1992 |
Construction of miscellaneous, concrete footings & foundation |
30 |
MINISTRY OF DEFENCE & AVIATION (DIRECTORATE GENERAL OF MILITARY WORKS) |
|
CONSTRUCTION OF AMMUNATION & WEAPON STORAGE STRUCTURE (IGLOO TYPE & ADMIN BLDG. - DHAHRAN |
|
12/1992 |
05/1994 |
Site preparation, construction of re-informed concrete storage structureIGLOO type, concrete retaining walls & floors, antiblast doors & valves, security fencing, admin offices , mechanical & standby electrical system w/ generator units |
31 |
MINISTRY OF DEFENCE & AVIATION (DIRECTORATE GENERAL OF MILITARY WORKS) |
|
CONSTRUCTION OF PRINCE SULTAN MOSQUE - HAFR AL-BATIN – PROJECT/M/7/15 |
|
03/1992 |
05/1993 |
Site preparation, foundation excavation, concrete foundations & walls, concrete structure complete, mosque tower, interior/exterior finishing, mechanical, electrical, utility & sanitary system, pre-cast concrete fence, landscaping & beautification wo |
32 |
SAUDI ARABIAN MARKETING & REFINING CO. (SAMAREC) – SAUDI ARAMCO |
|
SAFETY & SECURITY IMPROVEMENTS AT DHAHRAN BULK PLANT TERMINAL FACILITIES PROJECT 90-PO267 |
|
10/1991 |
06/1992 |
Reinforced concrete protection walls for fuel tanks (spill containment), concrete footings & foundations, installation of fabric fence type SSD-1 – electrical system & lighting network, - asphalt pavingreinforced concrete collection basin for excess |
33 |
DEPT. OF U.S. ARMY HQ – US ARMY CENTRAL COMMAND |
|
DISASSEMBLY/ASS EMBLY, CLEAN & PARK CLAMSHELL AIR CRAFT HANGERS PROJECT DASA01-91-C0057 |
|
08/1991 |
11/1991 |
Removal & disassemble clamshell structure inventory, clean & park clamshell structures & store, transport, reassemble & re-erect |
34 |
ROYAL COMMISSION FOR JUBAIL & YANBU – DIRECTORATE OF JUBAIL WORKS |
|
P & C MATERIALS HANDLING CARRIDORS & NORTH-WEST PUMPING STATION PROTECTION SYSTEM PROJECT 149-C11 |
|
12/1990 |
09/1992 |
Construction of security fence – 26km, guard rails – 13.5km, concrete barriers – 1.3km, gate house building patrol road – 2.5km, security lighting system |
35 |
MINISTRY OF DEFENCE & AVIATION (DIRECTORATE GENERAL OF MILITARY WORKS) |
|
CONSTRUCTION OF WAREHOUSE FOR MILITARY USE – HAFR AL-BATIN – PROJECT 2/12/15 |
|
01/1990 |
06/1991 |
Grading & preparation of the site, construction of steel buildings, concrete footings, foundation & floor, asphalt paving (roads & parking), construction of maintenance building, electrical system & lighting, safety equipments, chain link fence SSD-1 |
36 |
MINISTRY OF DEFENCE & AVIATION (DIRECTORATE GENERAL OF MILITARY WORKS) |
|
CONSTRUCTION OF STEEL SHELTER FOR HEAVY & LIGHT TRUCKS & CARS – KING FAHD MILITARY CITY DHAHRAN |
|
04/1989 |
04/1990 |
Grading &site preparation, backfilling works, construction of steel buildings (06nos.), asphalt paving total area 25,000sq.m., concrete floor 9,000sq.m., concrete foundation & footings, construction of maintenance building, electrical system & lighti |
37 |
MINISTRY OF DEFENCE & AVIATION (DIRECTORATE GENERAL OF MILITARY WORKS) |
|
UPGRADING OF HALF MOON RECREATION CENTER |
|
08/1989 |
04/1991 |
Grading & site preparation, construction of beach umbrellas w/ concrete floor & grid irons, water tanks, lighting of the site & electrical system, irrigation works, construction of roads & parking lots of the site & chain link fence length 550LM, lan |
38 |
MINISTRY OF DEFENCE & AVAITION (ROYAL AIR DEFENCE FORCES) |
|
CONSTRUCTION OF BUILDINGS FOR HEAVY & LIGHT VEHICLES PARKING LOT – ABQAIQ SITE PROJECT# 23/M/407 |
|
01/1989 |
07/1989 |
Grading & preparation of site, backfilling & compaction, concrete foundation & footings, construction of concrete buildings, asphalt paving (roads & parking), chain link fence around the site |
39 |
SALINE WATER CONVERSION CORP. (S.W.C.C.) |
|
PERIMETER SECURITY FENCE SSD-1 FOR KHOBAR DESALINATION PLANT SEASIDE |
|
01/1989 |
07/1989 |
Removal of old fence, concrete foundation & footings, site preparation, installation of new chain link fence type SSD-1 & single & double leaf gates, installation of barbed wire type, lighting system |
40 |
SALINE WATER CONVERSION CORP. (S.W.C.C.) |
|
|
|
01/1988 |
01/1989 |
Removal of old fence, concrete foundation & footings, site preparation, installation of new chain link fence type SSD-1 & single & double leaf gates, installation of barbed wire type, lighting system |
41 |
SALINE WATER CONVERSION CORP. (S.W.C.C.) |
|
PERIMETER SECURITY FENCE SSD-1 CHAINLINK FABRIC FENCE FOR JUBAIL DESALINATION PLANT (SEA SIDE |
|
11/1987 |
09/1988 |
Removal of old fence, concrete foundations and footings, installation of new chain link fence type SSD-1 single & double leaf gates, installation of barbed wire, guardhouse & gates, electrical system & lighting |
42 |
NATIONAL GUARD DEPUTY HQ OF EASTERN PROVINCE |
|
PERIMETER PRECAST FENCE FOR NATIONAL GUARD COMPOUND IN DAMMAM |
|
10/1987 |
03/1989 |
Removal of old fence, grading & preparation of site concrete footings & foundations construction & erection of pre-cast concrete fence by total length 12km |
43 |
SALINE WATER CONVERSION CORP. (S.W.C.C.) |
|
PRECAST CONCRETE FENCE FOR THE TANK OF STORAGE AREA – JUBAIL CITY |
|
10/1986 |
06/1987 |
Removal of old fence, concrete foundation & footings, construction of precast concrete fence, guardhouse & gates, electrical system & lighting |
44 |
MINISTRY OF DEFENCE & AVAITION (ROYAL AIR DEFENCE FORCES) |
|
CONSTRUCTION OF BUILDING FOR HEAVY & LIGHT VEHICLES PARKING LOT – ABU ALI – JUBAIL SITE |
|
11/1986 |
09/1987 |
Grading & preparation of site, backfilling & compaction, concrete foundation & footings, construction of concrete buildings, asphalt paving (roads & parking), chain link fence around the site including gates & watch towers, beautification of site & l |
45 |
MINISTRY OF DEFENSE AND AVIATION (MODA) |
2/6/134 |
CONSTRUCTION OF FACILITIES FOR LAND FORCES AVIATION GROUP |
Dharan |
January 2011 |
24 Months |
Construction of Facilities for Land Forces Aviation Group Site Work and Complete Finishing Works (Civil/Electrical/Mechanical/Communication Fire System, Suppression System, Helipad Lighting System & Asphalt Works), parking lot with the required acces |